Which statement is true about Project Scheduling?

a. Slack is defined as the difference between the earliest start and the latest finish of a task.

b. The critical path seldom has a slack time of zero.

c. Project crashing is an effort to maximize project duration.

d. The earliest finish for a task is equal to the early start plus the task duration.

e. None of the above statements are true.

 