The last step in activity-based costing is to

A.  compute the activity-based overhead rate per cost driver.

B.  identify and classify the major activities involved in the manufacture of specific products.

C.  assign manufacturing overhead costs for each activity cost pool to products.

D.  identify the cost driver that has a strong correlation to the activity cost pool.

Solution Description

The last step in activity-based costing is to