In a network diagram, an activity:

A.  should always be something the company has had experience with.

B.  must always have a single, precise estimate for the time duration.

C.  is the largest unit of work effort consuming both time and resources that a project manager can schedule and control.

D.  is the smallest unit of work effort consuming both time and resources that a project manager can schedule and control.

 