In a network diagram, an activity: - 2777

Solution Posted by
UoPExpert

UoPExpert

Rating : (2)F
Solution Detail
Price: $1.30
  • From: ,
  • Posted on: Wed 21 Mar, 2012
  • Request id: None
  • Purchased: 0 time(s)
  • Average Rating: No rating
Request Description

 In a network diagram, an activity:

A.  should always be something the company has had experience with.

B.  must always have a single, precise estimate for the time duration.

C.  is the largest unit of work effort consuming both time and resources that a project manager can schedule and control.

D.  is the smallest unit of work effort consuming both time and resources that a project manager can schedule and control.

 
Solution Description

In a network diagram, an activity: