A project has three paths. A–B–C has a length of 25 days. A–D–C has a length of 15 days. Finally, A–E–C has a length of 20 days. Which one of the following statements is TRUE?

A.  The expected duration of this project is 25 days.

B.  The expected duration of this project is 25 + 15 + 20 = 60 days.

C.  A–D–C is the critical path.

D.  A–B–C has the most slack.

 
Solution Description

A project has three paths. A–B–C has a length of 25 days. A–D–C has a length of 15 day