A labor efficiency variance resulting from the use of poor quality materials should be charged to:
 
the industrial engineering department.
 
manufacturing overhead.
 
the production manager.
 
the purchasing agent.
                                       

Solution Description

 

A labor efficiency variance resulting from the use of poor quality materials should be charged to:
 
the industrial engineering department.
 
manufacturing overhead.
 
the production manager.
 
the purchasing agent.